Supertech twin towers demolition: Building strong, built in seismic zone, says Joe Brinkmann

The twin buildings, which comprise 915 flats and are located just nine metres from Emerald Court's Aster-2 apartment block, have been fully rigged with explosives and wired up in August 28. A seven-member team of Jet Demolitions along with Edifice Engineering will bring down the twin towers with a controlled blast at 2.30 p.m. on Sunday (August 28). This will be the tallest towers to be demolished in the country.

Joe Brinkmann, CEO and managing director of Jet Demolitions, a South African-based firm which will carry out Supertech's illegal Twin Towers demolition along with Mumbai-based Edifice Engineering and others, said bringing down the twin towers is one of the most difficult tasks, building is strong and built in seismic zone.

The twin buildings, which comprise 915 flats and are located just nine metres from Emerald Court's Aster-2 apartment block, have been fully rigged with explosives and wired up in August 28.

Advertisement

A seven-member team of Jet Demolitions along with Edifice Engineering will bring down the twin towers with a controlled blast at 2.30 p.m. on Sunday (August 28). This will be the tallest towers to be demolished in the country.

"We are just doing preparations for the final day. We are just making checks for the final day so that there are no disturbances. It is one of the most difficult tasks, building is strong and built in seismic zone", said Joe Brinkmann while talking to media.

Advertisement

He said, "But we have designed the plan and implemented it to meet the challenges. The progression of the blast -- the buildings will be pulled away from North from aster-2 towards the south and then collapse".

He said that the Edifice Engineering will be handling the debris which will be cleaned up within three months.

Advertisement

According to the evacuation plan, over 5,000 residents of Emerald Court and ATS Village will have to vacate the premises by 7.30 a.m. on August 28. They will be allowed to return only after safety clearance from the officials is obtained.

Edifice Engineering, the Mumbai-based demolition company, has loaded some 7,000 drilled holes with explosives.

Advertisement

As per Edifice Engineering officials and members of the Emerald Court RWA, sprinklers and some other equipment will be used to settle down the dust with the help of over 150-odd housekeepers.